Scope of Work:

Southern Environmental, Inc. provided detailed engineering, material supply, fabrication, construction management, a 1/12 scale physical model study, electrical wiring, foundation, field construction, insulation and cladding, painting and start-up services for the utility's Unit #3 & Unit #4 Electrostatic Precipitator Project Replacement.

 

The new precipitator is upstream of a new FGD. The unique construction approach allowed for the addition of a future SCR to be located upstream of the ESP and reduced projected outage time by 50%.

Major North Carolina Utility 2007

Application:

2 - 700 MW Coal Fired Power Boiler Unit #3 & #4

 

Project Duration:

PO Received: October 2004

Mobilize: April 2005

Demobilize: May 2007

12 week outage

 

Detailed Engineering in the following Disciplines:

Civil Engineering

Structural Engineering

Mechanical Engineering

Electrical Engineering

1/12th Scale Physical Model Study

 

Fabrication and Erection Services:

Caisson Installation

Structural Steel Fabrication and Erection

ESP Fabrication and Erection

Electrical Construction

Ductwork Fabrication and Erection

Project Management

Site Management

Insulation and Lagging

Painting

Lead Abatement

 

Performance Guarantee:

SEI provided a broad range of guarantees for twenty-five coals. Outlet Emissions: Ranging between 0.04 #/mmBtu and 0.05 #/mmBtu Opacities: Ranging between 12% Opacity and 10% Opacity Inlet Gas Flow: 2,512,000 ACFM at 320 F

 